Design, Build, Commission and operation (7 years) for the enlargement of the Fujairah desalination plant.
The enlargement will give rise to 137,000 m3/day additional capacity—bringing the original plant’s total capacity to 592,000 m3/day—and the plant is expected to serve a population equivalent of 600,000 inhabitants.
The desalination plant has entered into service in March 2016. The contract includes the operation and maintenance until the year 2023
Emirates SembCorp Water & Power Company, a public-private Enterprise, has awarded ACCIONA, a Design, Build, Commission and Operate (7 years) contract for the enlargement of the Fujairah desalination plant, located in the Emirate of the same name.
The contract includes Design, Build and Commissioning of the Al Jubail RO4 100,000 m3/day seawater desalination plant.
EPC Contract. Its capacity of 210,000 m3/day makes it one of the largest desalination plants in the Eastern Province.